The National Land Commission (NLC) has defended its role in compensating landowners affected by the construction of the Isiolo-Mandera Highway following concerns raised by the World Bank over delays in the compensation process.
In a statement issued on Wednesday, November 18, the Commission rejected claims that it was responsible for the delays, explaining that the bulk of the compensation process, including the processing and disbursement of payments to affected landowners, falls under the Kenya National Highways Authority (KeNHA).
NLC clarified that its mandate is limited to conducting land valuations, verifying affected assets and preparing compensation schedules, while KeNHA handles the release of funds in accordance with World Bank directives.
"The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," NLC stated.

"It is worth noting that the Commission is only engaged in undertaking valuations and development of compensation schedules, with the role of processing of funds and disbursement of compensation funds to the PAPs being done by KeNHA as per World Bank directive and implementation of the HOAGDP," it added.
The clarification comes after the World Bank raised concerns over delays in land compensation, which have affected progress on the 740-kilometre highway.
In a letter addressed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir and Lands CS Alice Wahome, the Bank's Kenya Division Director, Qimiao Fan, warned that the delays had slowed construction and increased the risk of additional project costs.
The World Bank disclosed that the project was incurring more than Ksh1.2 billion in additional costs every month as contractors were unable to access sections of the land without restrictions, preventing them from carrying out construction as scheduled.
The lender also identified several affected sections, revealing that only 1,281 out of the 1,669 Project Affected Persons (PAPs) had received compensation.
In its response, NLC outlined the progress made in verifying assets and approving compensation payments across various sections of the highway, with approved payments running into billions of shillings.
Along the Isiolo-Kulamawe-Modogashe section, the Commission disclosed that compensation payments were ongoing, with KeNHA awaiting the World Bank's no-objection approval to pay 1,280 affected persons a total of Ksh554.9 million.
For the Wajir-Kotulo section, NLC has approved compensation for 1,619 affected persons, amounting to Ksh824 million.
Additionally, the Commission approved Ksh497 million in compensation for 296 Project Affected Persons along the Isiolo-Kachuru section.
On the Dimu-Elwak stretch, NLC reported that it had completed asset verification involving more than 1,105 affected persons. The valuation exercise is expected to be finalised by the end of November 2026.
"These milestones demonstrate the Commission's continued commitment to progressing land acquisition and compensation processes under the project," NLC said.
Despite the progress, the Commission identified several challenges that continue to hinder land acquisition and compensation, pointing to ongoing court disputes over payments as a major obstacle.
Other challenges include insecurity along the project route, landowners who have not collected their compensation offers and difficulties tracing some of the affected property owners.
The 740-kilometre Isiolo-Mandera Highway is being constructed under the Horn of Africa Gateway Development Project, which was 60 per cent complete as of October 26.
The project was initially scheduled for completion in January 2028. However, the World Bank subsequently revised the expected completion timeline to around 2030.